ROYAL MARSDEN (FULHAM ROAD, CHELSEA) NEW ENDOSCOPY UNIT
Creating a new Endoscopy Department on the Ground Floor of the
Main Building





Engaged on a negotiated basis on this particularly complex and potentially disruptive project.
Our early involvement and knowledge of the building ensured that all aspects of the M&E works were considered and planned in careful detail to minimise disruption to the Hospital.
The works comprised part new extension and part refurbishment. The new extension construction was particularly complex, with a new steel frame built within an existing lightwell, with the principal structural base and columns very carefully positioned alongside existing plant in a boiler room below.
Services
-
HWS/CWS Services
-
Ventilation
-
T.H.W.
-
Mains Cold Water
-
Public Health Services
-
Medical Gases
-
Controls
-
General Lighting
-
General Power
-
Fire Alarms
-
Nurse call
-
CCTV/security
Project Details | |
---|---|
Value | 515K including PC sums |
Construction period | 32 Weeks |
Designers/Consultants | Richard Stephens Partnership |
Designers/Engineers | Richard Stephens Partnership |
Project Managers | (Hospital) |
Quantity Surveyors | WT Partnership |
Architects | Ansell & Bailey |
Client | Royal Marsden NHS Foundation Trust |